Stripping Ratio: Formula, Units and How to Calculate It

The stripping ratio is the amount of waste that has to be moved to release one unit of ore. It is the first number anyone asks about an open pit, because waste costs money to move and only ore pays for it. The formula is a single division; the mistakes come from what is put into it — which unit, which density, which part of the pit. This guide covers the formula, the two unit conventions, the overall, incremental and break-even ratios, and where the waste and ore figures come from.

Stripping ratio calculator

Waste moved per tonne of ore. Enter the waste as an in-place volume or as a tonnage; with a waste density the calculator gives both conventions. Three optional cost figures give the break-even ratio.

Waste entered as
m³
t
t/m³
Stripping ratio (volume per tonne)1.2 m³/t
Stripping ratio (tonne per tonne)enter the waste density
Break-even stripping ratioenter the three cost figures

Formula: SR = W / O · SR(t/t) = SR(m³/t) · ρ · BESR = (v − c) / w

W: waste · O: ore tonnage · ρ: waste density · v: value per tonne of ore · c: cost per tonne of ore · w: cost per tonne of waste

Waste volume is in-place (bank) volume, not loose volume after swell. Use the density of the waste rock, not of the ore. The break-even ratio compares the margin on one tonne of ore with the cost of moving one tonne of waste, all three in the same currency; it ignores the time value of money and is not a pit optimisation.

A real site is rarely this regular. Measure the surveyed surface instead: Mining Block Model Software

The formula

Stripping ratio = waste removed ÷ ore recovered. A pit that moves 3 million tonnes of waste to mine 1 million tonnes of ore has a stripping ratio of 3, usually written 3:1.

Waste here means everything inside the excavation that is not sent to the plant: overburden, barren rock, and mineralised blocks that fall below the cut-off grade. That last part matters — raise the cut-off and some ore becomes waste, so the same pit has a higher stripping ratio without a single block having moved.

Two units, and a factor of waste density between them

The ratio is quoted in two ways. In metal mining both sides are tonnages, so the ratio is tonnes of waste per tonne of ore and carries no unit. In coal and many industrial-mineral operations the waste is quoted as an in-place volume: cubic metres per tonne, or cubic yards per ton.

The two are linked by the density of the waste: ratio in t/t = ratio in m³/t × waste density. Take 1,200,000 m³ of waste and 1,000,000 t of ore. By volume the ratio is 1.2 m³/t. If the waste rock weighs 2.5 t/m³, that is 3,000,000 t of waste and the ratio is 3.0 t/t. Same pit, same day, and one figure is two and a half times the other — which is why a stripping ratio without its unit cannot be compared with anything.

Stripping ratio conventions
ConventionWaste measured asOre measured asWhere it is usual
t/tTonnesTonnesMetal mines
m³/tIn-place cubic metresTonnesCoal and industrial minerals
yd³/tonIn-place cubic yardsShort tonsUS coal and non-metal operations

Overall, incremental and break-even

The overall stripping ratio is total waste over total ore for the whole pit. It describes the deposit as designed and is the figure quoted in a study.

The incremental — or instantaneous — stripping ratio is the ratio of one slice: the next bench down, or the next pushback of the wall. It is the waste that slice exposes over the ore that slice releases, and it normally rises with depth, because each bench has to carry the pit walls further out to reach it.

The break-even stripping ratio is an economic limit, not a measurement: the ratio at which the margin on a tonne of ore is spent entirely on the waste moved to reach it. Break-even ratio = (recoverable value per tonne of ore − cost of mining and processing that tonne) ÷ cost of stripping one tonne of waste. If a tonne of ore returns 25, costs 8 to mine and process, and waste costs 3 a tonne to move, the break-even ratio is (25 − 8) ÷ 3 = 5.7 t/t.

The comparison that decides how deep a pit goes is the incremental ratio against the break-even ratio, not the overall ratio. A pit can have a comfortable overall ratio and still be losing money on its last bench.

By bench, and cumulative to depth

Tabulate waste and ore bench by bench and two columns follow. The bench ratio is the incremental ratio of that bench. The cumulative ratio is all waste down to and including that bench over all ore down to it — the overall ratio the pit would have if it stopped there.

Read together, they show where the pit stops paying: the cumulative ratio moves slowly, the bench ratio moves first. The bench where the bench ratio crosses the break-even ratio is the one to look at, whatever the cumulative column says.

Where the two numbers come from

Waste and ore are not measured separately; they are a split of one volume. The excavation is the volume between the ground as surveyed and the pit design. The ore is the part of a block model that falls inside that excavation and above the cut-off grade, converted to tonnes with the density stored in the model. Waste is the rest of the excavation.

So the ratio is only as good as three inputs: the survey that fixes today's surface, the design that fixes the final one, and the block model that says what lies between them. A ratio computed against last year's surface counts waste that has already been moved.

What usually goes wrong

Mixing the conventions is the common one: a volume-based ratio from one report set against a tonnage-based ratio from another. Using the ore density for the waste is the quiet one — the two rocks rarely weigh the same, and the error passes straight into the t/t figure.

Loose volumes are the third. A stripping ratio uses in-place volume; truck counts and dump surveys measure material after swell, which is larger. And where a bench contains no ore, its ratio is undefined, not zero — a zero would read as a bench with no waste.

Stripping ratio in STREAM

STREAM's block model module reports the stripping ratio as part of the bench plan. It intersects an imported block model with the surveyed terrain and the pit design, and for every bench gives ore tonnage, waste and the stripping ratio, with cumulative ore and cumulative ratio beside them. The unit is chosen explicitly — t/t or m³/t — and printed next to every figure; until it is chosen, no ratio is written.

Waste tonnage uses the waste density set on the design, not the density of the ore blocks, and a tonnage-based ratio stays blank when no waste density has been given rather than being filled with an assumption. STREAM does not compute a break-even ratio and does not optimise the pit limit; it reports the ratio of the pit you designed.

Frequently asked questions

What is a stripping ratio?

The amount of waste that has to be removed to recover one unit of ore in an open pit. A ratio of 3:1 means three units of waste are moved for every unit of ore.

How do you calculate the stripping ratio?

Divide the waste removed by the ore recovered: stripping ratio = waste ÷ ore. Use tonnes on both sides for a t/t ratio, or in-place cubic metres of waste over tonnes of ore for m³/t. The calculator on this page gives both when a waste density is entered.

What is the difference between t/t and m³/t?

The waste density. Ratio in t/t = ratio in m³/t × waste density, so 1.2 m³/t with waste at 2.5 t/m³ is 3.0 t/t. Metal mines usually quote t/t; coal and industrial-mineral operations usually quote volume per tonne.

What is the break-even stripping ratio?

The ratio at which the margin on a tonne of ore is entirely spent on stripping: (recoverable value per tonne of ore − mining and processing cost per tonne of ore) ÷ stripping cost per tonne of waste. A slice of the pit with a higher incremental ratio than this costs more than it returns.

What is a good stripping ratio?

There is no single figure. A ratio is acceptable when it is below the break-even ratio for that ore, and the break-even ratio depends on grade, price, recovery and costs. A high-value ore carries a ratio that would close a low-value operation.

Does STREAM calculate the stripping ratio?

Yes, from an imported block model cut against the surveyed terrain and the pit design: by bench and cumulative, in t/t or m³/t as you choose. It does not compute a break-even ratio or optimise the pit limit.

Read ore, waste and stripping ratio bench by bench in STREAM

Native Windows · fully offline · free beta

Mining Block Model Software